Compare Schedules shows what changed. Analyse Revisions shows how the project is evolving.

Analyse Revisions

Review a single schedule or track project finish, activities and performance across up to five revisions.

Analyse revisions →

Common questions

Choosing a tool

Which tool should I use?

Use Compare Schedules to see what changed between two schedules. Use Analyse Revisions to follow how a project's schedule evolves across updates, or to review one schedule on its own.

Is it free? Do I need an account?

Both tools and their PDF reports are free. No account or signup required.

Can I compare a recovery plan or a what if scenario?

Yes. Reference is your starting point. Comparison is the schedule you assess against it. They can be a baseline and delayed plan, a delayed plan and recovery plan, or any two alternatives. They do not have to be successive monthly updates.

Can I compare two revisions inside historical analysis?

Use Compare Schedules for a focused comparison of any two files. Analyse Revisions shows all your uploaded schedules. Select a point on the finish chart to assess that revision against the first schedule. The other charts continue to show every upload.

Files and revisions

Which files can I upload?

Use Microsoft Project (.mpp) or Primavera P6 (.xer). Compare Schedules requires exactly two files of the same format. Analyse Revisions accepts one to five files, all MPP or all XER.

What are the upload limits?

Up to 25 MB per file, 50 MB in total and 20,000 activities per workspace. Larger or unusually complex schedules may exceed the processing limits.

What if my XER contains several projects?

Choose the project before analysis. Only the selected project is retained in your temporary workspace.

What order should my revisions be in?

For Analyse Revisions, upload oldest to newest. Manage revisions lets you label, reorder, replace and remove schedules. Use recorded data dates to check the order. Filenames do not determine the sequence.

Can I replace a file without starting again?

In Analyse Revisions, use Manage revisions to replace, add, remove or reorder schedules. In Compare Schedules, choose New comparison to upload a different pair.

Understanding results

Can I investigate a specific activity or milestone?

Use Explore an activity on either results page. Search any recorded name or ID, or choose Milestones. Select an activity to see its dates, duration, progress, float, Critical Path and constraints across the uploaded schedules. Connections shows its recorded predecessors and successors for each schedule, with expandable chains and links to connected activities.

Are connection chains driving paths?

No. They show the relationships recorded in the uploaded schedule. The imported data does not identify driving links, so GanttScan does not label a relationship as driving or claim it caused a delay.

Does GanttScan recalculate my schedule or critical path?

No. It analyses recorded source values and imported critical flags. It does not reschedule work, recalculate CPM or determine what caused a delay.

How are activities matched if IDs change?

Matching considers source identity, names, hierarchy and schedule context. Renumbering alone does not mean work was added or removed. Use Review a match to check or adjust a specific match.

What does added or removed mean?

The activity has no accepted match in the other schedule. This may reflect changed scope or an uncertain match. Review major restructuring and duplicate activity names in context.

Are days calendar days or working days?

Date movements use elapsed calendar days. Duration, float and lag values retain the source units shown. Float movement requires compatible units and calendar definitions.

Which progress figures does GanttScan use?

Choose a progress type after uploading each file. The options come from its recorded fields, such as % complete, Work % complete or Physical % complete. XER files can also use each activity’s recorded completion method. Changes are shown only when the methods are comparable. The headline uses the percentage recorded in the project summary when available. It does not average activity percentages.

Why isn't there an overall project completion percentage?

A simple average of activity percentages can be misleading. GanttScan shows recorded activity progress and counts without inventing a project weighting.

Are health findings errors?

They are items to review, not a compliance score. The dashboard shows open ends and date constraints, linked to the affected activities. Both can be appropriate for your project. Check the activities in your source schedule before deciding whether they need attention.

Why is a figure unavailable?

A required source value may be missing or not comparable. Missing values are excluded rather than treated as zero. Inspect the activity history to see the source values and where a comparison is unavailable.

Privacy and reports

Are my files changed or saved?

Your original files are not changed. Temporary uploads are deleted after extraction. Extracted data and settings remain in a private temporary workspace for up to 30 minutes, with no permanent project history. You can delete that workspace yourself.

What does each PDF report contain?

Compare Schedules provides a report showing values before and after comparison for the selected analysis sections. Analyse Revisions includes historical summaries, milestone history and selected activity evidence. Download before the workspace expires. Large reports may require selecting fewer sections or exporting individual views as CSV.

Does analysis happen in my browser?

Schedule parsing and analysis use the server. XER project selection can be prepared locally in your browser. Schedule content is not sent to the analytics provider. See the Privacy Policy for details.